Schedule 1A + NES-DMRU · plain-English guideCHECK YOUR COUNCIL

New Zealand rules guide · checked September 2026

The 70 m² consent exemption, in plain English.

A qualifying detached minor home may proceed without a building consent and without a resource consent. Those are two separate legal pathways, and each has conditions. This guide shows what the national rules settle, what still needs a property check, and the order to do the work.

In force 15 January 2026Schedule 1ANES-DMRU
A detached small home in a rural New Zealand setting
Illustrative Seventy small-home design
01Start here

Two different consents, two different tests

The reforms work together, but neither one proves that the other applies. A project that falls outside either set of conditions must follow the normal consent pathway for that part of the work.

70 m²
Maximum internal floor areaMeasured to the internal face of the external walls. An attached or internally accessed garage counts inside it.
2 m
Minimum distance from the main homeDistances are measured from the outside face of the wall cladding.
1
Detached minor dwelling per siteOne detached minor residential unit per site.
The building consent exemptionSchedule 1A

Building consent, if all Schedule 1A conditions are met

The national planning standardNES-DMRU

Resource consent, if all relevant requirements are met

02What changed

The two national reforms

Both took effect on 15 January 2026. They apply prospectively and do not retrospectively approve an existing dwelling.

01
The building consent exemption
Instrument

Schedule 1A, under the Building Act 2004

What it removes

Building consent, if all Schedule 1A conditions are met

How it works

A new, detached, single-storey home up to 70 m² may be built without a building consent if every exemption condition is met. Licensed professionals, Building Code compliance, a Project Information Memorandum and council notifications are still required.

02
The national planning standard
Instrument

NES-DMRU, under the Resource Management Act 1991

What it removes

Resource consent, if all relevant requirements are met

How it works

The national planning standard can permit one detached minor dwelling without resource consent when its standards and other relevant requirements are met. Some district and regional rules remain, including those for hazards, infrastructure and earthworks.

Announced change · effective 8 October 2026
More products and servicing options from 8 October

From 8 October, certified composite structural products can be used within their CodeMark scope, and qualifying projects may be able to use or modify existing water, wastewater and stormwater services. Utility approval, system capacity and Building Code compliance still apply. Read the Building Performance, MBIE.

03National measurements

Floor area, coverage and setbacks

These are the NES-DMRU permitted-activity standards for qualifying detached minor dwellings. A district plan can be more generous. Other property restrictions can still affect the building position or trigger consent.

StandardResidential zoneRural zone
Maximum internal floor areaMeasured to the internal face of the external walls. An attached or internally accessed garage counts inside it.70 m²70 m²
Maximum area of the site covered by buildingsThe 50% standard overrides any district plan coverage standard below 50% in a residential zone.50%As required by the zone
Minimum distance from the main homeDistances are measured from the outside face of the wall cladding.2 m2 m
Minimum distance from the front boundary2 m10 m
Minimum distance from side and rear boundaries2 m5 m

The permitted-activity rule: One detached minor residential unit per site. The standard applies in residential, rural, mixed use and Māori purpose zones, as defined in the National Planning Standards, or the equivalent zones where a council has not implemented them yet.

Source: Ministry for Cities, Environment, Regions and Transport, September 2026 (INFO 1387). Read the source for the complete requirements and definitions.

04Eligibility

Check the home and the site

These are the main eligibility questions to resolve before relying on the national pathways. They are a starting point; every relevant condition still needs to be met.

01
Detached home
What it means

The minor dwelling must be physically separate from the principal home. An attached extension is assessed under different requirements.

02
Principal home on the same site
What it means

The NES-DMRU planning standard requires a minor dwelling to be secondary to a principal home on the same site and in the same ownership. If both are proposed together, confirm the construction order and requirements with the council.

03
One minor dwelling per site
What it means

The NES-DMRU allows one detached minor dwelling per site. For a cross-lease, the site includes all the land under the cross-lease. A district plan may allow more, subject to its requirements.

04
New dwelling for Schedule 1A
What it means

The building consent exemption applies to new dwellings. A building conversion may meet the planning standard, but it is not covered by this building consent exemption.

Sources: Ministry for Cities, Environment, Regions and Transport, September 2026 (INFO 1387) and Building Performance, MBIE.

05What still applies

National permission is not a blank cheque

The NES-DMRU removes a defined group of district-plan controls for a qualifying proposal. It does not remove natural-hazard, infrastructure, title and other relevant requirements.

District-plan controls the NES-DMRU removes
  • Special character, design guides and visual amenity
  • Screening for rubbish and recycling storage
  • Wall and roof colour, reflectivity and external finishes
  • Minimum outdoor open space, privacy or sunlight access
  • Minimum window area
  • Parking
  • Minimum site size
Property checks that remain
  • Natural hazards
  • Water, wastewater and stormwater
  • Electricity lines and infrastructure
  • Nearby activities and contaminated land
  • Earthworks and subdivision
  • Heritage and cultural sites
  • Title restrictions and bylaws
  • Council contributions
01
Natural hazards
Check council maps

Flooding, coastal hazards, fault lines and land stability can affect the building location, floor level and need for consent. Check the council information and obtain site advice where needed.

02
Water, wastewater and stormwater
Check the property requirements

Check connection requirements and capacity. Relevant regional plan rules still apply, including requirements for an on-site wastewater system.

03
Electricity lines and infrastructure
Check council maps

Buildings near electricity lines and other significant infrastructure must meet the relevant safe-distance and planning requirements.

04
Nearby activities and contaminated land
Check council maps

Rules can apply near airports, ports, industry and farming operations, or on contaminated land. They may affect where a home can be built and what design measures are needed.

05
Earthworks and subdivision
Check the property requirements

Earthworks may need resource consent even when the dwelling does not. Subdivision requirements are separate and remain in place.

06
Heritage and cultural sites
Check council maps

Relevant protections for heritage, cultural sites and outstanding natural features still apply.

07
Title restrictions and bylaws
Check the property title

Check covenants and easements on your property title. The national planning standard does not override private covenants, and more stringent council bylaws can still apply.

08
Council contributions
Check the property requirements

Development and financial contributions may be payable. Ask your council to confirm which charges apply to your project.

Keep the two tests separate
Planning permission does not confirm building consent exemption

A district plan may allow a larger home or a smaller boundary setback. That does not change the separate Schedule 1A requirements. For example, an 80 m² dwelling or a 1 m setback would not meet the 70 m² and 2 m conditions for this building consent exemption.

06Project sequence

Do the checks before the build

The property title, planning layers and service capacity can change the viable building position. Resolve them before finalising plans or starting construction.

01
Review the property title
What happens

Check covenants and easements that could restrict a second home, its size, location or access.

02
Check planning requirements
What happens

Review council maps and relevant district and regional rules for natural hazards, infrastructure and other restrictions.

03
Confirm service connections
What happens

Identify the water, wastewater and stormwater connections and confirm capacity. Check any requirements for an on-site wastewater system.

04
Obtain a PIM
What happens

Apply for and receive a Project Information Memorandum before construction starts. It records the council information relevant to the property and proposed work.

05
Finalise the plans
What happens

Your designer confirms the design requirements for the property and prepares the required plans and documentation. The Schedule 1A exemption requires appropriately licensed professionals.

06
Complete the building notifications
What happens

Notify the council before construction and provide the required completion documents afterwards. Your designer and builder must supply the records and certificates required for their work.

07Questions

Frequently asked questions

Do I need building consent for a granny flat?+

A new, detached, single-storey dwelling up to 70 m² may qualify for the Schedule 1A exemption if every condition is met. The Building Code, licensed-professional requirements and council documentation still apply. Obtain a Project Information Memorandum before starting and provide the required notifications and completion records.

Will I need resource consent?+

The NES-DMRU can allow a qualifying detached minor dwelling without resource consent. The project must meet its standards and relevant district and regional requirements. Rules for matters such as hazards, earthworks and infrastructure may still require consent.

What floor area and setbacks are allowed?+

The national planning standards allow up to 70 m² internal floor area. In residential zones, the standards include 50% maximum building coverage and 2 m setbacks from the principal home and boundaries. Rural boundary setbacks are 10 m at the front and 5 m at the sides and rear, with coverage set by the zone. Check the table above and any other site restrictions.

Can district plans set different measurements?+

District plans can provide more generous measurements than the NES-DMRU. Equivalent district-plan measurements that are more restrictive do not apply to a qualifying proposal. Other relevant requirements, including natural-hazard and infrastructure restrictions, can still apply.

What local requirements still apply?+

Check natural hazards, service connections, infrastructure, nearby activities, contaminated land, earthworks, subdivision and heritage or cultural protections. Relevant regional plan rules also apply. Your council can confirm the requirements for your property and intended use.

Can a property title restrict the project?+

Yes. Covenants and easements can restrict building even where planning rules allow it. Obtain the title documents and get advice on any restriction that may affect the proposal. Relevant council bylaws also need to be checked.

Can I use the planning standard on vacant land?+

The NES-DMRU is for a minor dwelling associated with a principal home on the same site. A small home built first on vacant land is assessed as the principal home under the relevant district plan. This planning requirement is separate from eligibility for the building consent exemption.

Can the home be rented out?+

Residential rental use can be allowed, subject to the relevant requirements. Healthy Homes Standards and tenancy obligations apply where relevant. Small-scale short stays may qualify where secondary to residential use; confirm the proposed use with your council.

08Official sources

Read the rules at source

This guide is an orientation, not a substitute for the legislation, official guidance or property-specific advice. Confirm the current requirements for your address before construction.

Checked against these sources in September 2026. Confirm the current requirements for your property before construction.

Start with the property checks.

Tell us the address and the small-home design you are considering.

DISCUSS YOUR PROJECTSEE THE DESIGNS
CALL USSEE THE DESIGNS